| Sl No. |
Client |
Job Description |
Rounded off in Rs Cr. |
Rounded off in US $ in millions |
Start |
Expected Completion |
Domestic/ Overseas |
| PROJECTS UNDER EXECUTION |
| 2 |
HMCPCL, Haldia |
Handling, erection , testing and commssioning of Coke oven machines Phase 1 &2 for HMCPCL, Haldia, West Bengal |
2 |
0.5 |
Nov-06 |
2009 |
Domestic |
| 3 |
RINL |
Modification of Continuous Bloom caster 2 in steel Melting Shop at Vizag steel Plant, AP |
33 |
7 |
Dec-07 |
2009 |
Domestic |
| 4 |
Tata Steel |
Supply & Erection of Mechanical items & Utilities for Top Recovery Turbine (TRT) at 'G’ Blast furnace at Tata Steel, Jamshedpur. |
4 |
1 |
Dec-07 |
2009 |
Domestic |
| 5 |
Bhushan Steel |
Equipment erection, fabrication and rerection of pipes and structural steel for coke oven machine plant at Meeramandali Orissa |
53 |
12 |
Mar-08 |
2010 |
Domestic |
| 6 |
Steel Authority of India Ltd |
Hot Metal Desulphurisation for SMS-II for Bokaro Steel plant 7 Million Ton expansion on divisible turnkey basis. |
54 |
12 |
Jul-08 |
2010 |
Domestic |
| 7 |
Steel Authority of India Ltd |
Design, supply and construction of 1x4060 cum 5th Blast Furnace for Rourkela Steel Plant |
1250 |
280 |
Jul-08 |
2011 |
Domestic |
| 8 |
Steel Authority of India Ltd |
Turnkey contract for Interplant Piping including Gas mixing stations (Pkg24) at IISCO Steel Plant, Burnpur, West Bengal. |
151 |
34 |
Jun-09 |
2010 |
Domestic |