| Sl No. |
Client |
Job Description |
Rounded off in Rs Cr. |
Rounded off in US $ in millions |
Start |
Completed |
State |
PROJECTS EXECUTED |
| 1 |
ONGC, Gandhar, Ankleshwar |
Turnkey construction of additional condensate recovery unit for LPG augumentation at CPF, ONGC, Gandhar, Gujarat |
15 |
3 |
Feb-06 |
2008 |
Gujarat  |
| 2 |
Tata Power Company Limited, Mumbai |
Fuel Oil Tanks/Chimney for 4 x10 MW DG Power Plant for TPCL at Khopoli(TPCL Lodhivali I), Maharashtra |
8 |
2 |
Jan-07 |
2008 |
Maharashtra |
| 3 |
Chemplast & Sanmar Ltd |
Supply and erection of Seawater Intake & Brine Reject Outfall System including all Civil work to Chemplast & Sanmar Ltd Cuddalore Tamil Nadu |
11 |
2 |
Aug-07 |
2008 |
Tamil Nadu |
| 4 |
ISRO, SHAR |
Supply of equipments & fabrication and erection of SS piping for Propellent Bulk storage tank for ISRO, SHAR (ISRO2), AP |
3 |
1 |
Sep-07 |
2008 |
Andhra Pradesh |
| 5 |
ISRO - Government of India, Department of Space |
Design, preparation of drgs., manufacture & erection, testing & commissioning of casting facility equipment at SHAR, Sriharikota, AP |
18 |
4 |
Jan-06 |
2009 |
Andhra Pradesh |
  |
| Sl No. |
Client |
Job Description |
Rounded off in Rs Cr. |
Rounded off in US $ in millions |
Start |
Expected Completion |
State |
PROJECTS UNDER EXECUTION |
| 1 |
HPCL |
Mechanical/Piping works for NIU,FCC-NHT units of Visakh Refinery clean fuel projects(HPCL I), AP. |
25 |
6 |
May-06 |
2010 |
Andhra Pradesh |
| 2 |
HPCL |
Erection of equipment and machinery, fabrication and erection of piping etc for utilities and offsites of Visakh Refinery Clean Fuel Project. (HPCL- II), AP. |
13 |
3 |
Nov-06 |
2010 |
Andhra Pradesh |
| 3 |
TPCL |
Electro mechanical works of Malle Nallah Diversion near Bhira Hydro power station , Maharashtra |
6 |
1 |
Apr-07 |
2010 |
Maharashtra |
| 4 |
ONGC |
L.P. Gas Processing and Compression Facilities at Rajahmundry , AP |
130 |
29 |
Feb-08 |
2010 |
Andhra Pradesh |
| 5 |
ONGC, Ankleshwar |
"EPC of Gas Collecting Station Expansion Project at Olpad near Surat, Gujarat |
7 |
2 |
Jul-08 |
2010 |
Gujarat |
| 6 |
Bharat Petroleum Corp Ltd (BPCL) |
Mechanical works for VGO/HDS Units (Part A) for CEMP II of BPCL-Kochi Refinery. The work includes Turnkey erection packages for the main refinery units including erection services of two Main Reactors of 800 MT and 200 MT in the main package of the refinery unit. |
55 |
12 |
Oct-08 |
2010 |
Kerala |
| 7 |
Bharat Petroleum Corp Ltd (BPCL) |
Mechanical works for NHT/CCR Units (Part B) for CEMP II of BPCL-Kochi Refinery. The work includes Turnkey erection packages for the main refinery units. |
45 |
10 |
Oct-08 |
2010 |
Kerala |
| 8 |
ONGC Ankaleshwar |
Supply, Installation and commissiong of Steam heater in CSU Train at CPF, Gandhar (ONGC, Gandhar 2) |
3 |
1 |
Oct-08 |
2010 |
Gujarat |
| 9 |
Cairn Eneregy India Pty Ltd |
EPC of Radhanpur terminal for Mangala Development Pipeline project |
80 |
18 |
Jan-09 |
2010 |
Gujarat |
| 10 |
NPCIL- Kudankulam, O&M |
O&M of desalination Plant for 5 years at Kudankulam, Tamilnadu |
46 |
10 |
Oct-09 |
2014 |
Tamil Nadu |
| 11 |
HPCL |
Duct fabrication for FCCU-II at Visakh Refinery, Vizag |
3 |
1 |
Feb-10 |
2010 |
Andhra Pradesh |
| 12 |
Tata Power Company Limited, Mumbai |
BOP for 4x10.56 DG set power plant(TPCL Lodhivali II) , Maharashtra |
9 |
2 |
Apr-07 |
2010 |
Maharashtra |