| Sl No. |
Client |
Job Description |
Rounded off in Rs Cr. |
Rounded off in US $ in millions |
Start |
Expected Completion |
Domestic/ Overseas |
PROJECTS UNDER EXECUTION |
| 1 |
ISRO - Government of India, Department of Space |
Design, preparation of drgs., manufacture & erection, testing & commissioning of casting facility equipment at SHAR, Sriharikota, AP |
18 |
4 |
Jan-06 |
2009 |
Domestic |
| 2 |
HPCL |
Mechanical/Piping works for NIU,FCC-NHT units of Visakh Refinery clean fuel projects(HPCL I), AP. |
29 |
6 |
May-06 |
2009 |
Domestic |
| 4 |
HPCL |
Erection of equipment and machinery, fabrication and erection of piping etc for utilities and offsites of Visakh Refinery Clean Fuel Project. (HPCL- II), AP. |
17 |
4 |
Nov-06 |
2009 |
Domestic |
| 5 |
TPCL |
Electro mechanical works of Malle Nallah Diversion near Bhira Hydro power station , Maharashtra |
6 |
1 |
Apr-07 |
2009 |
Domestic |
| 8 |
ONGC |
L.P. Gas Processing and Compression Facilities at Rajahmundry , AP |
137 |
30 |
Feb-08 |
2009 |
Domestic |
| 9 |
ONGC, Ankleshwar |
EPC of Gas Collecting Station Expansion
Project at Olpad near Surat, Gujarat
|
7 |
2 |
Jul-08 |
2009 |
Domestic |
| 10 |
Utico FZC |
Detailed Engg Services for proposed 20 MW captive Power Plant for Utico at Technology Park, RAK FTZ, UAE |
1 |
0.25 |
Aug-08 |
2009 |
Overseas |
| 11 |
RAKGAS LLC |
EPC of Utico Zamil Steel gas distribution network at UAE |
9 |
2 |
Aug-08 |
2009 |
Overseas |
| 12 |
M/s RAKGAS LLC, UAE |
Revamping the controls of Bukha Gas Processing train, UAE |
19 |
4 |
Oct-08 |
2009 |
Overseas |
| 13 |
Bharat Petroleum Corp Ltd (BPCL) |
Mechanical works for VGO/HDS Units (Part A) for CEMP II of BPCL-Kochi Refinery. The work includes Turnkey erection packages for the main refinery units including erection services of two Main Reactors of 800 MT and 200 MT in the main package of the refinery unit.
|
57 |
13 |
Oct-08 |
2009 |
Domestic |
| 14 |
Bharat Petroleum Corp Ltd (BPCL) |
Mechanical works for NHT/CCR Units (Part B) for CEMP II of BPCL-Kochi Refinery. The work includes Turnkey erection packages for the main refinery units.
|
45 |
10 |
Oct-08 |
2009 |
Domestic |
| 15 |
ONGC Ankaleshwar |
Supply, Installation and commissiong of Steam heater in CSU Train at CPF, Gandhar (ONGC, Gandhar 2) |
3 |
0.75 |
Oct-08 |
2009 |
Domestic |
| 16 |
Cairn Eneregy India Pty Ltd |
EPC of Radhanpur terminal for Mangala Development Pipeline project |
80 |
18 |
Jan-09 |
2009 |
Domestic |
| 17 |
NPCIL, Mumbai |
O&M of Desalination Plant, constructed on EPC basis and based on MVC technology at Kudankulam Nuclear Power Project , Tamil Nadu |
50 |
11 |
Jun-09 |
2014 |
Domestic |