Sl No. |
Client |
Job Description |
Project Value* |
Start |
Completion |
State |
| In Rs Cr. |
In Million USD |
PROJECTS EXECUTED |
| 1 |
Central Organization for Railway Electrification, Allahabad |
Design, Supply, Erection, Testing & Commissioning of 25kV Single Phase, 50Hz, Traction Overhead Equipment, Switching Stations and LT Supply Transformer stations in Talcher - Angul section and seven sidings of Eastern Railways, Orissa. |
5 |
1 |
Mar-06 |
2007 |
Orissa |
| 2 |
Central Organization for Railway Electrification, Allahabad |
Design, Supply, Erection, Testing & commissioning of 25kV, Single Phase, 50 hz, Traction Overhead Equipments, Switching Stations, LT supply transformer stations and Booster transformer stations on Tirupati-Pakala-Katpadi Section of Southern Central Railway |
30 |
6 |
Oct-06 |
2007 |
Andhra Pradesh |
| 3 |
DRDO (Govt. of India Ministry of Defence Research & Development Organization) |
Provision of Rail Track cum Road at Misa , Assam for DRDO |
45 |
10 |
Feb-07 |
2009 |
Assam |
| 4 |
Rail Vikas Nigam Limited |
Supply Erection Testing & Commissioning of 25 kV, 50 Hz, Single Phase in connection with patch doubling of Pullampet (Excl) - Nandalur (Incl) section of Guntakal Division |
10 |
2 |
Sep-06 |
2009 |
Andhra Pradesh |
| 5 |
Rail Vikas Nigam Limited |
All civil work like major and minor bridges, FOB, Platform modification and connected electrical works in connection with the Gauge Conversion of Metre Gauge Railway Line to Broad Gauge Line of Villupuram - Mayiladuthurai Section of Southern Railway. |
160 |
36 |
Apr-06 |
2010 |
Tamil Nadu |
| |
Sl No. |
Client |
Job Description |
Project Value* |
Start |
Completion |
State |
| In Rs Cr. |
In Million USD |
PROJECTS UNDER EXECUTION |
| 1 |
Central Railway |
Conversion of 1500V DC OHE to 25000 V AC OHE incl. turnkey package of Transformers & Eqpt in Karjat-Lonawala part of Kalyan-Pune section of Mumbai division of Central Railways |
25 |
6 |
Jan-07 |
2011 |
Mahrashtra |
| 2 |
Core, Allahabad |
OHE of Khurja - Hapur- Meerut – Saharanpur section of Delhi & Muradabad Divisions of Northern Railway |
25 |
6 |
Jul-08 |
2011 |
Uttar Pradesh |
| 3 |
Rail Vikas Nigam Limited |
Design, Supply, Erection, testing & commissioning of 25 KV, 50 HZ, Single phase Traction Overhead equipment, switching stations and other associated works for Railway electrification between Kondapuram-Guntakal section of South Central Railway.
|
110 |
24 |
Nov-08 |
2011 |
Andhra Pradesh |
| 4 |
Southern Railway |
Design, Supply, erection, testing and commissioning of Traction overhead equipment, switching stations including modifications to the existing OHE between Chengalpattu-Olakur- OHE |
30 |
7 |
Feb-09 |
2012 |
Tamil Nadu |
| 5 |
Southern Railway |
Design, Supply, erection, testing and commissioning of Traction overhead equipment, switching stations including modifications to the existing OHE between Olakur- Villupuram OHE |
25 |
6 |
Feb-09 |
2012 |
Tamil Nadu |
| 6 |
GMR Kamalanga Energy Ltd |
Supply and erection for Railway Siding work for 1050 MW Thermal Power Plant at
Kamalanga Dist, Dhenkanal, Orissa
|
35 |
8 |
28.12.09 |
2011 |
Orissa |
| 7 |
CORE, Allahabad |
Overhead electrification of Madurai(Excl.)-Tuticorin-Vanchimaniyanchi-Nagercoil (Excl.) section (Gr.154) of Southern Railway, Tamil Nadu |
30 |
7 |
Feb-10 |
2012 |
Tamil Nadu |
| 8 |
Southern Railway |
Modification to the existing OHE at Tambaram-Arakkonam & Korukkupet of Chennai Division
|
10 |
2 |
June-10 |
2012 |
Tamil Nadu |
| 9 |
GMR EMCO Energy Ltd |
Railway Infrastructure for 2 x 300 MW coal based Thermal Power Plant at Warora, Maharashtra
|
40 |
9 |
Sep-10 |
2011 |
Mahrashtra |
| 10 |
CORE-Allahabad |
OHE of Varanasi to Allahabad Section of Northern Railway |
30 |
7 |
Nov-10 |
2012 |
Uttar Pradesh |
| 11 |
Rail Vikas Nigam Limited |
Design, Supply ,Erection ,Testing & Commissioning of Traction Overhead
Equipment, Switching Stations, Traction Sub-station, SCADA, Signaling &
Telecommunication work between Gooty - Dharmavaram - Yelahanka section of South
Central Railways & Bangalore Division of South Western Railways (355 TKM) |
140 |
31 |
Aug 11 |
2013 |
Karnataka |