  Projects Executed - Transmission & Distribution  
 
Project List updated up to August  2011
 
 
* Rounded off as appropriate
 
 

Sl No.

Client

Job Description

Project Value*

Start 

Completion 

State

In Rs Cr. In Million USD

PROJECTS EXECUTED-DOMESTIC

1 POWERGRID, Patna  Installation and commissioning of 400 kV, 2 nos, 50 MVAR reactors at Sarnath 400 Kv Substation of UPPCL  of 400 kV D/C Bihar-Sharif-Sasaram- TL
1
0
Dec-00
2001
Bihar
2 Sumitomo Corpn., Tokyo  Supply & Installation of 400 kV XLPE Power Cable Project at Srisailam Left Bank 
10
2
Feb-00
2002
Andhra Pradesh
3 Maharashtra State Electricity Board, Maharashtra  Turnkey execution of 132 kV & 33 kV Substations including interconnecting lines under Power System Improvement Project in Jalna System in Jalna District (OECF MSEB) 
20
4
Mar-00
2003
Maharashtra 
4 Maharashtra State Electricity Board, Maharashtra  Turnkey execution of 132 kV & 33 kV Substations including interconnecting lines under Power System Improvement Project in Nilanga System in Latur District (OECF MSEB) 
25
6
Mar-00
2003
Maharashtra 
5 Kerala State Electricity Board, Kozhikode  Turnkey execution of 110/33 kV / 11 kV Substation (1 no.), 33 / 11 kV Substations (3 nos.) and 33 kV Transmission Lines and 11 kV Transmission Lines, 11 kV (5 nos.), 600 KVAR capacitors Distribution Project at Palakkad district of Kerala 
15
3
Apr-01
2003
Kerala
6 POWERGRID, Gurgaon  Supply and erection  of equipment and materials for 220kV Transmission Lines associated with Transmission System Strengthening of Electricity Department, Government of Goa
10
2
Dec-01
2003
Maharashtra 
7 Haryana Vidyut Prasaran Nigam Ltd., Hisar,Haryana  Supply and Installation of 220 kV Double Circuit Transmission Line from Palli to Badshapur for Haryana State Power Sector Restructuring Project 
5
1
Mar-00
2004
Haryana 
8 TataTelecom Ltd., Gurgaon,New Delhi  SDH Backbone Network -Civil works, supply and services for 28 new backbone sites for Birla AT & T 
10
2
 
Aug-00
2004
 Delhi 
9 Haryana Vidyut Prasaran Nigam Ltd., Haryana  Supply and erection  of equipment for turnkey construction of 220 kV and 132 kV Transmission Lines for 220 kV Substation at Rania and 132 kV Substations at Madhosinghana, Ellenabad, Kariwala and Odhan 
15
3
Jun-01
2004
Haryana 
10 Haryana Vidyut Prasaran Nigam Ltd., Haryana  Supply and erection 220 kV and 132 kV TL for 220 kV Substation at Cheeka and 132 kV Substations at Chakuladana, Padla
10
2
Jun-01
2004
Haryana 
11 Kerala State Electricity Board, Thiruvananthapuram  Construction of 220 kV D/C LILO Lines, (twin moose, and single moose.) to 220 kV Substations at Kundra and Edappon from the 220 kV Kayamkulam - Edamon double circuit feeder on turnkey basis 
40
9
May-01
2005
Kerala
12 POWERGRID, Gurgaon  Supply and erection of  Equipment & Material for 400 kV D/C Dhauliganga (NHPC) -Bareily (UPPCL) Transmission Line under Dhauliganga Transmission System 
70
16
Mar-02
2005
Uttar Pradesh
13 POWERGRID, Gurgaon  400 KV Extension Bays  Stage -III Project -  Supply of goods for Substation Package "B" [Extension of 400 KV Kurnool, Gooty and Nelamangala
15
3
Apr-02
2005
Andhra Pradesh
14 ADWEA  Lot (1)-Installation of 33/11 kV, 15 MVA Package Units -(3 nos.) at Wadi Sulaimi & Meryal Al Ain. Lot (2)-Installation of 33/11 kV, 15 MVA Transformers at Zakher Grid. 
5
1
Apr-02
2005
Gujarat
15 POWERGRID, Gurgaon  Supply and erection of 400 KV Extension Bays from Power Grid for Ramagundam Stage -III Project,Package “B” 
15
3
Jun-02
2005
Andhra Pradesh
16 POWERGRID, Gurgaon  Supply and erection  of equipment / materials for construction of 400kV D/C Tarapur - Boisar Line, LILO of 400 kV SIC Gandhar - Padghe Line at Boisar and 220 kV S/C Tarapur-Boisar Line (P-A1) for Tarapur Extension Transmission system 
25
6
Jul-03
2005
Maharashtra 
17 New Delhi Power Ltd. (NDPL), Delhi  Supply and erection of High Voltage Distribution System (HVDS), Ibrahimpur Extension 
1
0
Jul-03
2005
Uttar Pradesh
18 New Delhi Power Ltd. (NDPL), Delhi  Supply and erection of High Voltage Distribution System (HVDS), Kadhi Vihar, Dist. Narela 
2
0
Aug-03
2005
Delhi
19 POWERGRID, Gurgaon  Supply and erection of 33 kV underground cable for alternate power supply to Panjim in North Goa Circle of Electricity Department, Government of Goa 
5
1
Oct-03
2005
Maharashtra 
20 POWERGRID, Gurgaon  Detailed survey of Transmission Lines associated with RAPP-C Transmission System using Modern Survey Techniques like Satellite Imageries, Total Stations, GPS 
1
0
Mar-04
2005
Delhi
21 POWERGRID, Gurgaon  Detailed survey of Transmission Lines associated with Sipat-ll Supplementary Transmission System & System Strengthening Scheme-l of WR using Modern Survey Techniques 
1
0
Jun-04
2006
Uttar Pradesh
22 POWERGRID, Gurgaon  Supply and erection of equipment and materials for Tower Package (package-C) for 400 kV DC Vishnuprayag  –Muzaffarnagar Transmission Line Part III 
60
13
Oct-03
2006
Uttar Pradesh
23 POWERGRID, Gurgaon  Detailed survey of transmission lines associated with NRSS-V transmission system using modern survey techniques like satellite imageries, total stations, GPS etc. 
1
0
Dec-04
2006
Delhi
24 POWERGRID, Gurgaon  Detailed survey of transmission lines associated with RAPP 5 & 6 supplementary transmission system using modern survey techniques like satellite imageries, total stations, GPS etc. 
1
0
Dec-04
2006
Delhi
25 POWERGRID, Nagpur  Detailed survey of transmission lines associated with Kawas II and Gandhar II (project) using modern survey techniques -Package B 
1
0
Feb-05
2006
Gujarat
26 POWERGRID, Nagpur  Detailed survey of transmission lines associated with Kawas II and Gandhar II (project) using modern survey techniques -Package C 
1
0
Feb-05
2006
Gujarat
27 TPCL, Kolkata  400 kV D/C Kanpur -(Package - A) Auriya Transmission Line 
10
2
Apr-05
2006
Uttar Pradesh
28 POWERGRID, Gurgaon  Design, Engineering, Manufacture, Factory Testing, Supply, Erection including associated Civil works, Testing & Commissioning of 400KV bay extension at Kishenpur Substation
55
12
Jul-05
2006
Uttar Pradesh
29 Tata Power Company Limited  Design, Procurement, Testing and supply of components excluding OPGW materials & aviation lights, for a 220 kV four circuit transmission line at Trombay 
5
1
Mar-06
2006
Maharashtra 
30 Tata Power Company Limited  Erection, Testing, commissioning of new four circuit line and dismantling of existing 2 x 110 kV ICT 4/5 & 2 x 220 kV MSEB Tie lines 
1
0
Mar-06
2006
Maharashtra 
31 POWERGRID, Gurgaon  Construction, Testing & Commissioning of 400 KV D/C Ranchi-Pillki  transmission lines
25
6
Oct-05
2007
Jharkhand
32 TPCL, New Delhi  Construction of tower package (package A1) 400 kV D/C (QUAD) Seoni -Khandwa Transmission Line Part II associated with Sipat
30
7
Dec-04
2007
Madhya Pradesh
33 POWERGRID, Gurgaon  supply and erection of equipment and materials for turnkey package for diversification / modification of existing 400 kV D/C Uri-Wagoora-Pampore Transmission Line 
40
9
Aug-04
2007
Jammu & Kashmir
34 TPCL, New Delhi  Construction of 400kV D/C Thathar-Wagoora Transmission Line (Package B) for POWERGRID in the state of Jammu & Kashmir 
35
8
Aug-02
2007
Jammu & Kashmir
35 Tata Steel Design, manufacture, supply and delivery of Optical ground wire and accessories for 132 KV Transmission lines from Golmuri to MRSS Substation.
1.0
0
Mar-07
2007
Jharkhand
36 TPCL, New Delhi  Construction of 400kV D/C Kishenpur-Thathar Transmission Line (Package A) for POWERGRID in the state of Jammu & Kashmir 
55
12
Aug-02
2008
Jammu & Kashmir
37 TPCL, New Delhi  Erection of 400kV D/C Darjeeling-New Siliguri Section of Teesta-V HEP -New Siliguri Transmission Line (Package B) 
35
8
May-05
2008
Assam
38 POWERGRID, Jammu Installation of 3 nos. Towers in left circuit of 400 KV Kishenpur- wagoora line in Peer-Panjal area for replacement of collapsed L11 & L18 towers, J&K
2
0
Mar-07
2008
Jammu & Kashmir
39 Uttranchal Power Corporation Limited Electrification of Villages & their households on turnkey basis at Pauri, Uttranchal
90
20
Dec-05
2009
Uttranchal
40 Uttranchal Power Corporation Limited Electrification of Villages & their households on turnkey basis at Chamoli, Uttranchal
50
11
Dec-05
2009
Uttranchal
41 UPCL Additional work of Pauri-II Rural Electrification  work on Turnkey basis , Uttaranchal
25
6
Feb-08
2009
Uttaranchal
42 UPCL Additional work of Chamoli-II Rural Electrification work on Turnkey basis, Uttaranchal
15
3
Feb-08
2009
Uttaranchal
43 Tata Power Company Limited  132 kV Transmission Line and related modifications for line from Jojobera to Tata Steel , Jharkhand
15
3
Dec-06
2009
Jharkhand
44 JUSCO Supply and erection of 132 kV Transmission Line Project from Golf Club to Bara to Sonari (Pkg B), Jharkhand
5
1
Dec-06
2009
Jharkhand
45 JUSCO Supply and erection of  132 KV Transmission Line Project from Jojobera to Tata Growth Shop (Pkg C), Jharkhand
15
3
Dec-06
2009
Jharkhand
46 ACC – Bargarh Cement Works, Orissa    Supply and erection of 33KV Overhead TL & associated switchyards and civil work  at ACC- Bargarh cement works on turnkey basis including supply of maintenance spares & commissioning spares
10
2
Apr-07
2009
Orissa
47 M/S Industrial Energy Limited  Supply, Erection, Testing & Commissioning of 132 kV Switchyard Bay Extension at Jojobera, Jamshedpur. 
10
2
May-08
2009
Jharkhand
48 POWERGRID, Gurgaon  Supply and erection of Tower Package G1 for 765 kV S/C Seoni Bina Transmission line , Madhya Pradesh
105
23
Jun-06
2010
Madhya Pradesh
49 POWERGRID, Gurgaon  Erection of 400kV D/C Tower Pkg. B under 3 & 4 Trans. System for Mysore-Kutta TL 
20
4
Dec-05
2010
Karnataka

PROJECTS EXECUTED-OVERSEAS

1 United Development Consultants, Doha, Qatar  Design and Construction of Primary Electrical HV Substations (CP/2-2), Qatar 
480
107
Dec-05
2009
Qatar
 
     