  Projects Executed - Transmission & Distribution  
     
 

Sl No.

Client

Job Description

Start

Completion

Domestic/ Overseas

COMPLETED PROJECTS (BEFORE SBU FORMATION)

1

Tavanir Co., Ministry of Energy, Iran

Tariff Study in Tehran

1991

1992

Overseas

2

Kudremukh Iron Ore Co.Ltd., Karnataka

Electrical & Instrumentation of Relocation of Crusher-Ill

1993

1994

Domestic

3

ABB SAE Sadelmi SpA, Milan, Italy

Installation of Electrical, Instrumentation and Control Equipment of 732 MW and 250,000 Cu.M/day for Al Taweelah “B” Power and Desalination Plant at Abu Dhabi

1994

1997

Overseas

4

Nuclear Power Corpn., Kaiga, Karnataka

Electrical installation works at 2 x 500 MW Nuclear Power Plant

1994

1999

Domestic

5

Andhra Pradesh State Electricity Board, AP

Transmission Lines from Nellore to Renigunta 220 kV DC (58 Km)

1994

1995

Domestic

6

Andhra Pradesh State Electricity Board, AP

Transmission Lines (220 kV) DC from a) Kothagudem Thermal Power Station to Khammam with Twin Moose conductor (75 Km) b) Khammam to Bhongir (50 Km)

1994

1997

Domestic

7

Water& Electricity Dept., Abu Dhabi

Reinforcement of 33 kV Network (total 27 Substations) in Abu Dhabi & Al Ain areas on turnkey basis

1995

1998

Overseas

8

POWERGRID, New Delhi

400 kV Indravathi Switching Station (extn.) supply-cum-erection package

1995

1999

Domestic

9

Andhra Pradesh State Electricity Board, AP

3 x 33 kV Substations in Madikonda

1996

1998

Domestic

10

Sharjah Oil Refining Co. Ltd, Sharjah

Installation work of Electrical & Instrumentation items at Al Hamriya Oil Refinery Project

1997

1998

Overseas

11

Andhra Pradesh Industrial Infrastructure Corpn., Ltd., AP

Electrical installation work for INT,Gachibowli, AP -Turnkey installation including supply and civil works

1997

1998

Domestic

12

Nepal Electricity Authority, Nepal

Design, Manufacture, Supply, Transportation, Storage at Site, Erection, Testing & Commissioning of 132 kV Transmission Lines (114 KM) and 2 Nos. Substations for Kaligandaki “A” Hydro Electric Project at Lot 07 in Kathmandu, Nepal

1998

2001

Overseas

13

Andhra Pradesh State Electricity Board, Hyderabad

Design, Supply, Transport, Erection, Testing & Commissioning of 132/33 kV and 33/11 kV Substations with Associated Transmission Lines and augmentation work for APSEB-OECF system improvement project at Nizamabad (South System)

1998

2000

Domestic

14

Andhra Pradesh State Electricity Board, Hyderabad

Supply and Erection of VTS-Chillakallu 220 kV DC Line

1998

1999

Domestic

15

Haryana State Electricity Board, Haryana

Design, Manufacture, Supply, Transportation, Storage at Site, Erection, Te sting & Commissioning of 220 kV DC Transmission Line from Yamunanagar to Shahabad, Palla to Pali and Samayapur to Pali in Haryana (58.6 Kms)

1998

2001

Domestic

16

Andhra Pradesh State Electricity Board, Hyderabad

Construction of 30 KM 33 KV Transmission Line on turnkey basis for Puttamgandhi Pumping Station, Nalgonda District, AP

1998

1999

Domestic

17

OECF for Grid Corpn. of Orissa Ltd, Bhubaneshwar

System Improvement Project -220/33 KV; 132/33 KV, 33/11 KV and 33 KV Transmission Lines for 75 kms Distribution & Substation works

1998

2001

Domestic

18

Andhra Pradesh State Electricity Board, Hyderabad

Construction of 220 kV Multi-circuit Transmission Line from Chandrayanagutta to Gachibowli, Hyderabad

1998

2000

Domestic

19

Haryana State Industrial Development Corpn, New Delhi

Execution of electrical works for Bawal Investate Growth Centre, Haryana State

1998

2003

Domestic

20

Tata Iron & Steel Co. Ltd., Jamshedpur

Supply & Engineering, Procurement & Construction of Lighting System for Cold Rolling Mill Project

1998

2000

Domestic

21

GEC Alstom, Chennai for Neyveli Lignite Corp. Ltd., Neyveli, Tamil Nadu

Civil works, supply of structures, erection, testing & commissioning of 400 kV and 200 kV Switchyard for Neyveli Lignite Corp. Ltd., Neyveli

1998

2001

Domestic

22

Grid Corpn. of Orissa Ltd., Bhubaneswar

132 kV Power System Improvement Projects in Bolangir District under OECF funded subprojects

1999

2002

Domestic

23

Grid Corpn. of Orissa Ltd., Bhubaneswar

132 kV Power System Improvement Projects in Sonepur Districts under OECF funded subprojects

1999

2002

Domestic

24

Andhra Pradesh State EB, Hyderabad

Erection & commissioning of 6 nos. 33/11 kV Substations and Transmission lines at Visakhapatnam, East Godavari,West Godavari, Srikakulam, Guntur and Nellore districts under System Improvement project

1999

2001

Domestic

25

Andhra Pradesh State Electricity Board, Hyderabad

Erection & commissioning of 6 nos. 33/11 kV Substations and Transmission lines at Warangal, Karimnagar, Nizamabad and Adilabad districts under System Improvement project

1999

2001

Domestic

26

Andhra Pradesh State Electricity Board, Hyderabad

Erection & commissioning of 6 nos. 33/11 kV Substations and Transmission lines at Mahaboobnagar and kurnool districts under System Improvement project

1999

2001

Domestic

27

Power Grid Corpn. of India Ltd., Patna thru’ Tata International Ltd.

Turnkey execution of 400 KV D/C Transmission Line Tower Package for AC Transmission System -Bihar Sharif -Sasaram with Power Grid Corpn. India Ltd.

1999

2001

Domestic

28

APTransco (SIP -Adaptable Programme Lending)

APL-1 Ranga Reddy , chittor, Anatapur, Kurnoll, Nizamabad, warangal, Medak, west goadavari, karimnagar, Nellore

1999

2001

Domestic

29

National Institute of Small Industry Extension Training (NISIET), Hyderabad

Design, supply, erection, testing and commissioning, of 11 kV / 415 V, 5OO kVA Transformer Substation

1999

2000

Domestic

30

Tata Electric Cos., Mumbai

Design, manufacture, s ho p t e s t i ng, supply, unloading, erection, testing and commissioning of Electrical Package of 2 x 120 MW Units II and III of Jojobera Power Plant, Jamshedpur

1999

2001

Domestic

31

Siemens, Germany

Design, supply and installation of Mechanical, Electrical & Instrumentation Works including refurbishment of Storage Water Tanks and DM Water Tanks of Water Treatment Plant for Combined Cycle Power Plant, Stage-Ill

1990

1983

Domestic

32

Alstom, Chennai

Supply of structures, erection, testing & commissioning of 220 kV Switchyard for Kondapalli Power Corpn. Ltd.

1999

2000

Domestic

 
 

COMPLETED PROJECTS (AFTER SBU FORMATION)

1

Sumitomo Corpn., Tokyo

Supply & Installation of 400 kV XLPE Power Cable Project at Srisailam Left Bank

Feb-00

2002

Domestic

2

Maharashtra State Electricity Board, Maharashtra

Turnkey execution of 132 kV & 33 kV Substations including interconnecting lines under Power System Improvement Project in Jalna System in Jalna District (OECF MSEB)

Mar-00

2003

Domestic

3

Maharashtra State Electricity Board, Maharashtra

Turnkey execution of 132 kV & 33 kV Substations including interconnecting lines under Power System Improvement Project in Nilanga System in Latur District (OECF MSEB)

Mar-00

2003

Domestic

4

Haryana Vidyut Prasaran Nigam Ltd., Hisar,Haryana

Supply and Installation of 220 kV Double Circuit Transmission Line from Palli to Badshapur for Haryana State Power Sector Restructuring Project

Mar-00

2004

Domestic

5

TataTelecom Ltd., Gurgaon,New Delhi

SDH Backbone Network -Civil works, supply and services for 28 new backbone sites for Birla AT & T

 Aug-00

2004

Domestic

6

POWERGRID, Patna

Installation and commissioning of 400 kV, 2 nos, 50 MVAR reactors and associated equipment at Sarnath400 Kv Substation of UPPCL for termination of 400 kV double circuit Bihar-Sharif-Sasaram-Allahabad Transmission Line

Dec-00

2001

Domestic

7

POWERGRID, Patna

Supply of equipment and materials for installation and commissioning of 400 kV, 2 nos. 50 MVAR reactors and associated equipment at Sarnath 400 kV Substation of UPPCL for termination of 400 kV double circuit Bhiar-Sharif-Sasaram-Allahabad Transmission Lin

Dec-00

2005

Domestic

8

Kerala State Electricity Board, Kozhikode

Turnkey execution of 110/33 kV / 11 kV Substation (1 no.), 33 / 11 kV Substations (3 nos.) and 33 kV Transmission Lines 30 kms. and 11 kV Transmission Lines 25 kms, 11 kV (5 nos.), 600 KVAR capacitors Distribution Project at Palakkad district of Kerala

Apr-01

2003

Domestic

9

Kerala State Electricity Board, Thiruvananthapuram

Construction of 220 kV D/C LILO Lines, 31.5 kms. (twin moose,23 kms and single moose,8.5 kms.) to 220 kV Substations at Kundra and Edappon from the 220 kV Kayamkulam - Edamon double circuit feeder on turnkey basis

May-01

2005

Domestic

10

Haryana Vidyut Prasaran Nigam Ltd., Haryana

Supply and erection  of equipment for turnkey construction of 220 kV and 132 kV Transmission Lines for 220 kV Substation at Rania and 132 kV Substations at Madhosinghana, Ellenabad, Kariwala and Odhan

Jun-01

2004

Domestic

12

Haryana Vidyut Prasaran Nigam Ltd., Haryana

Supply and erection of equipment for turnkey construction of 220 kV and 132 kV Transmission Lines for 220 kV Substation at Cheeka and 132 kV Substations at Chakuladana, Padla, Kangthali and Bhagal

Jun-01

2004

Domestic

14

POWERGRID, Gurgaon

Supply and erection  of equipment and materials for 220kV Transmission Lines associated with Transmission System Strengthening of Electricity Department, Government of Goa

Dec-01

2003

Domestic

16

POWERGRID, Gurgaon

Supply and erection of  Equipment & Material for 400 kV D/C Dhauliganga (NHPC) -Bareily (UPPCL) Transmission Line under Dhauliganga Transmission System

Mar-02

2005

Domestic

18

ADWEA

Lot (1)-Installation of 33/11 kV, 15 MVA Package Units -(3 nos.) at Wadi Sulaimi & Meryal Al Ain. Lot (2)-Installation of 33/11 kV, 15 MVA Transformers at Zakher Grid.

Apr-02

2005

Domestic

19

POWERGRID, Gurgaon

Supply and erection of 400 KV Extension Bays from Power Grid for Ramagundam Stage -III Project,Package “B”

Jun-02

2005

Domestic

21

TPCL, New Delhi

Construction of 400kV D/C Kishenpur-Thathar Transmission Line (Package A) for POWERGRID in the state of Jammu & Kashmir

Aug-02

2008

Domestic

22

TPCL, New Delhi

Construction of 400kV D/C Thathar-Wagoora Transmission Line (Package B) for POWERGRID in the state of Jammu & Kashmir

Aug-02

2007

Domestic

23

POWERGRID, Gurgaon

Supply and erection  of equipment / materials for construction of 400kV D/C Tarapur - Boisar Line, LILO of 400 kV SIC Gandhar - Padghe Line at Boisar and 220 kV S/C Tarapur-Boisar Line (P-A1) for Tarapur Extension Transmission system

Jul-03

2005

Domestic

25

New Delhi Power Ltd. (NDPL), Delhi

Supply and erection of High Voltage Distribution System (HVDS), Ibrahimpur Extension

Jul-03

2005

Domestic

27

New Delhi Power Ltd. (NDPL), Delhi

Supply and erection of High Voltage Distribution System (HVDS), Kadhi Vihar, Dist. Narela

Aug-03

2005

Domestic

29

POWERGRID, Gurgaon

Supply and erection of equipment and materials for Tower Package (package-C) for 400 kV DC Vishnuprayag  –Muzaffarnagar Transmission Line Part III

Oct-03

2006

Domestic

31

POWERGRID, Gurgaon

Supply and erection of 33 kV underground cable for alternate power supply to Panjim in North Goa Circle of Electricity Department, Government of Goa

Oct-03

2005

Domestic

33

POWERGRID, Gurgaon

Detailed survey of Transmission Lines associated with RAPP-C Transmission System using Modern Survey Techniques like Satellite Imageries, Total Stations, GPS

Mar-04

2005

Domestic

34

POWERGRID, Gurgaon

Detailed survey of Transmission Lines associated with Sipat-ll Supplementary Transmission System & System Strengthening Scheme-l of WR using Modern Survey Techniques

Jun-04

2006

Domestic

35

POWERGRID, Gurgaon

supply and erection of equipment and materials for turnkey package for diversification / modification of existing 400 kV D/C Uri-Wagoora-Pampore Transmission Line

Aug-04

2007

Domestic

37

POWERGRID, Gurgaon

Detailed survey of transmission lines associated with RAPP 5 & 6 supplementary transmission system using modern survey techniques like satellite imageries, total stations, GPS etc.

Dec-04

2006

Domestic

38

POWERGRID, Gurgaon

Detailed survey of transmission lines associated with NRSS-V transmission system using modern survey techniques like satellite imageries, total stations, GPS etc.

Dec-04

2006

Domestic

39

TPCL, New Delhi

Construction of tower package (package A1) 400 kV D/C (QUAD) Seoni -Khandwa Transmission Line Part II (115 km) associated with Sipat-l

Dec-04

2007

Domestic

40

POWERGRID, Nagpur

Detailed survey of transmission lines associated with Kawas II and Gandhar II (project) using modern survey techniques -Package B

Feb-05

2006

Domestic

41

POWERGRID, Nagpur

Detailed survey of transmission lines associated with Kawas II and Gandhar II (project) using modern survey techniques -Package C

Feb-05

2006

Domestic

42

TPCL, New Delhi

Erection of 400kV D/C Darjeeling-New Siliguri Section of Teesta-V HEP -New Siliguri Transmission Line (Package B)

May-05

2008

Domestic

43

TPCL, Kolkata

400 kV D/C Kanpur -(Package - A) Auriya Transmission Line

Apr-05

2006

Domestic

44

POWERGRID, Gurgaon

Design, Engineering, Manufacture, Factory Testing, Supply, Erection including associated Civil works, Testing & Commissioning of 400KV bay extension at Kishenpur Substation

Jul-05

2006

Domestic

45

Uttranchal Power Corporation Limited

Electrification of Villages & their households on turnkey basis at Pauri, Uttranchal

Dec-05

2007

Domestic

46

Uttranchal Power Corporation Limited

Electrification of Villages & their households on turnkey basis at Chamoli, Uttranchal

Dec-05

2007

Domestic

47

POWERGRID, Gurgaon

Construction, Testing & Commissioning of 400 KV D/C Ranchi-Pillki  transmission lines

Oct-05

2007

Domestic

49

Tata Power Company Limited

Design, Procurement, Testing and supply of components excluding OPGW materials & aviation lights, for a 220 kV four circuit transmission line at Trombay

Mar-06

2006

Domestic

50

Tata Power Company Limited

Erection, Testing, commissioning of new four circuit line and dismantling of existing 2 x 110 kV ICT 4/5 & 2 x 220 kV MSEB Tie lines

Mar-06

2006

Domestic

51

POWERGRID, Jammu

Installation of 3 nos. Towers in left circuit of 400 KV Kishenpur- wagoora line in Peer-Panjal area for replacement of collapsed L11 & L18 towers, J&K

Mar-07

2008

Domestic

52

Tata Steel

Design, manufacture, supply and delivery of Optical ground wire and accessories for 132 KV Transmission lines from Golmuri to MRSS Substation.

Mar-07

2007

Domestic

53

UPCL

Additional work of Pauri-II Rural Electrification  work on Turnkey basis , Uttaranchal

Feb-08

2009

Domestic

54

UPCL

Additional work of Chamoli-II Rural Electrification work on Turnkey basis, Uttaranchal

Feb-08

2009

Domestic

 